One method for optimizing
limited resources and reducing the possibility of equipment failures that
has been in use in the nuclear industry for some time now is risk-based
inspection. Risk-based inspection is a procedure for ranking or prioritizing
equipment for inspection purposes, based upon risk. Risk is the combination
of probability and consequence. Probability is the likelihood of an event
occurring, in this case an equipment failure. Consequence is a measure,
both in lives and property, of the damage that would occur if an equipment
item failed.
Risk based inspection
procedures can be based on either qualitative or quantitative methodologies.
Qualitative procedures provide a ranking of equipment, based largely on
experience and engineering judgement. Quantitative risk-based methods use
several engineering disciplines to set priorities and develop programs
for equipment inspection. Some of the engineering disciplines include nondestructive
examination, system and component design and analysis, fracture mechanics,
probabilistic analysis, failure analysis, and operation of facilities.
Quantitative analysis methods are expensive, time consuming, tedious and
are outside the scope of this document. Often, insufficient information
is available for conducting a quantitative risk analysis. Two organizations
that are currently working on quantitative risk-based analysis procedures
for use by the chemical industry are the American Society of Mechanical
Engineers and the American Petroleum Institute.
RBI Procedure
This document discusses
one approach for ranking process equipment, based on internal probability
of failure (POF). The procedure is based on an analysis of equipment process
and inspection parameters, and ranks equipment on a scale of one to three,
with "one" being the highest priority. The procedure requires
considerable use of engineering judgement and experience; therefore, the
results are dependent on the background and expertise of the analyst. The
procedure has been used to rank more than 2000 equipment items and is both
practical, effective and efficient.
The POF numerical
ranking arrived at using the procedure is not meant to be an indicator
of an equipment item's absolute susceptibility to failure. It is intended
as a convenient and reproducible means for establishing equipment inspection
priorities, based on knowledge. As such, it facilitates the most efficient
use of finite inspection monies and personnel where 100% inspection is
not practical
The procedure is
based on a set of rules heavily dependent on detailed inspection histories,
knowledge of corrosion processes, and knowledge of normal and upset conditions.
As such, the equipment rankings will not stay constant, but will require
updating as additional knowledge is gained, process conditions change and
equipment ages. Maximum benefits of the procedure depend on fixed equipment
inspection programs that permit the capture, documentation, and retrieval
of inspection, maintenance, and corrosion/failure mechanism information.
The POF procedure
is one-half of a risk-based inspection procedure. The POF ranking is combined
with a consequence ranking to provide a true risk-based ranking. A procedure
for ranking equipment based on consequence is also outside the scope of
this document; however, a similar procedure can be developed, using such
process attributes as flammability, reactivity, corrosivity, density, toxicity,
etc. The three rankings developed from the consequence analysis can be
combined with the probability rankings in a three-by-three matrix. Forty-five
degree parallel constant-risk lines result in five risk categories. These
categories can be used to establish inspection intervals, etc.
The equipment covered
by the procedure includes all fixed equipment to consider items designed
and constructed to ASME Section VIII, "Rules for Construction of Pressure
Equipment", divs. 1 and 2. They are not appropriate for rotating equipment.
The fixed equipment to consider on the procedure would normally be based
on OSHA's hazardous chemicals guideline; however, it can be used to rank
all equipment, if desired.
As failures can occur
from both internal and external causes, a similar procedure is required
to rank equipment based on external failures. This internal POF ranking
procedure is used for shutdown inspection planning. The external POF ranking
procedure is used to plan onstream inspections.
|